DEVELOPMENT OF PLUMBING DEVICE FOR STRUCTURAL STEEL COLUMN ERECTION
نویسندگان
چکیده
منابع مشابه
Subpart R—Steel Erection
(5) The limited access zone shall remain in place until the wall is adequately supported to prevent overturning and to prevent collapse unless the height of wall is over eight feet, in which case, the limited access zone shall remain in place until the requirements of paragraph (b) of this section have been met. (b) All masonry walls over eight feet in height shall be adequately braced to preve...
متن کاملSimulation for Steel Bridge Erection by Using Bim Tools
Steel bridge erection requires a series of processes in the construction site including shipping, sequentially lifting, and installing bridge components that are fabricated in the factory. Each process is critical and the risks are high due to the fact that conditions in the field are far more complex than in the factory. A detailed lifting plan is important to ensure the successful completion ...
متن کاملFabrication and Erection of Structural Steelwork
The steel-framed building derives most of its competitive advantage from the virtues of prefabricated components, which can be assembled speedily at site. Unlike concreting, which is usually a wet process conducted at site, steel is produced and subsequently fabricated within a controlled environment. This ensures high quality, manufacture offsite with improved precision and enhanced speed of c...
متن کاملSafety and environmental variables: effect on steel erection task durations
In 2002, the construction industry had the undesirable distinction of having two of the most dangerous occupations in the United States, with fatalities among structural steel workers at 58.2 fatalities per 100,000 workers (4 highest rate) and construction laborers experiencing fatalities at the rate of 27.7 fatalities per 100,000 workers (9 highest rate). In addition to the costs associated wi...
متن کاملStandard Product Models for Supporting Automated Erection of Structural Steelwork
A piece of automation equipment such as a robotic crane for steel erection has no intrinsic knowledge of the process it automates. Thus, geometric and spatial information about a component such as a steel member, and the motion sequences that must be executed to move that component from a staging area to its installed final location must both be programmed into the equipment. In automated steel...
متن کاملذخیره در منابع من
با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید
ژورنال
عنوان ژورنال: AIJ Journal of Technology and Design
سال: 2000
ISSN: 1341-9463,1881-8188
DOI: 10.3130/aijt.6.21_2