Proactive Algorithms for Scheduling with Probabilistic Durations

نویسندگان

  • J. Christopher Beck
  • Nic Wilson
چکیده

Proactive scheduling seeks to generate high quality solutions despite execution time uncertainty. Building on work in [Beck and Wilson, 2004], we conduct an empirical study of a number of algorithms for the job shop scheduling problem with probabilistic durations. The main contributions of this paper are: the introduction and empirical analysis of a novel constraint-based search technique that can be applied beyond probabilistic scheduling problems, the introduction and empirical analysis of a number of deterministic filtering algorithms for probabilistic job shop scheduling, and the identification of a number of problem characteristics that contribute to algorithm performance.

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Job Shop Scheduling with Probabilistic Durations

Proactive approaches to scheduling take into account information about the execution time uncertainty in forming a schedule. In this paper, we investigate proactive approaches for the job shop scheduling problem where activity durations are random variables. The main contributions are (i) the introduction of the problem of finding probabilistic execution guarantees for difficult scheduling prob...

متن کامل

A UNIFIED MODEL FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM WITH UNCERTAIN ACTIVITY DURATIONS

In this paper we present a unified (probabilistic/possibilistic) model for resource-constrained project scheduling problem (RCPSP) with uncertain activity durations and a concept of a heuristic approach connected to the theoretical model. It is shown that the uncertainty management can be built into any heuristic algorithm developed to solve RCPSP with deterministic activity durations. The esse...

متن کامل

ROBUST RESOURCE-CONSTRAINED PROJECT SCHEDULING WITH UNCERTAIN-BUT-BOUNDED ACTIVITY DURATIONS AND CASH FLOWS II. SOUNDS OF SILENCE: A NEW SAMPLING-BASED HYBRID PRIMARY-SECONDARY CRITERIA HARMONY SEARCH METAHEURISTIC

In this paper, we present a new idea for robust project scheduling combined with a cost-oriented uncertainty investigation. The result of the new approach is a makespan minimal robust proactive schedule, which is immune against the uncertainties in the activity durations and which can be evaluated from a cost-oriented point of view on the set of the uncertain-but-bounded duration and cost param...

متن کامل

Proactive Algorithms for Job Shop Scheduling with Probabilistic Durations

Most classical scheduling formulations assume a fixed and known duration for each activity. In this paper, we weaken this assumption, requiring instead that each duration can be represented by an independent random variable with a known mean and variance. The best solutions are ones which have a high probability of achieving a good makespan. We first create a theoretical framework, formally sho...

متن کامل

Uncertain Resource Availabilities: Proactive and Reactive Procedures for Preemptive Resource Constrained project Scheduling Problem

Project scheduling is the part of project management that deals with determining when intime to start (and finish) which activities and with the allocation of scarce resources to theproject activities. In practice, virtually all project managers are confronted with resourcescarceness. In such cases, the Resource-Constrained Project Scheduling Problem (RCPSP)arises. This optimization problem has...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:

دوره   شماره 

صفحات  -

تاریخ انتشار 2005