The problem of annual production scheduling in surface mining consists of determining an optimal sequence of extracting the mineralized material from the ground. The main objective of the optimization process is usually to maximize the total Net Present Value of the operation. Production scheduling is typically a mixed integer programming (MIP) type problem. However, the large number of integer variables required in formulating the problem makes it impossible to solve. To overcome this obstacle, a new algorithm termed ‘‘Fundamental Tree Algorithm’’ is developed based on linear programming to aggregate blocks of material and decrease the number of integer variables and the number of constraints required within the MIP formulation. This paper proposes the new Fundamental Tree Algorithm in optimizing production scheduling in surface mining. A case study on a large copper deposit summarized in the paper shows substantial economic benefit of the proposed algorithm compared to existing methods. 2006 Elsevier B.V. All rights reserved.
منابع مشابه
An imperialist competitive algorithm for solving the production scheduling problem in open pit mine
Production scheduling (planning) of an open-pit mine is the procedure during which the rock blocks are assigned to different production periods in a way that the highest net present value of the project achieved subject to operational constraints. The paper introduces a new and computationally less expensive meta-heuristic technique known as imperialist competitive algorithm (ICA) for long-term...
متن کاملORE extraction and blending optimization model in poly- metallic open PIT mines by chance constrained one-sided goal programming
Determination a sequence of extracting ore is one of the most important problems in mine annual production scheduling. Production scheduling affects mining performance especially in a poly-metallic open pit mine with considering the imposed operational and physical constraints mandated by high levels of reliability in relation to the obtained actual results. One of the important operational con...
متن کاملA genetic algorithm approach for open-pit mine production scheduling
In an Open-Pit Production Scheduling (OPPS) problem, the goal is to determine the mining sequence of an orebody as a block model. In this article, linear programing formulation is used to aim this goal. OPPS problem is known as an NP-hard problem, so an exact mathematical model cannot be applied to solve in the real state. Genetic Algorithm (GA) is a well-known member of evolutionary algorithms...
متن کاملA Comprehensive Study of Several Meta-Heuristic Algorithms for Open-Pit Mine Production Scheduling Problem Considering Grade Uncertainty
It is significant to discover a global optimization in the problems dealing with large dimensional scales to increase the quality of decision-making in the mining operation. It has been broadly confirmed that the long-term production scheduling (LTPS) problem performs a main role in mining projects to develop the performance regarding the obtainability of constraints, while maximizing the whole...
متن کاملDevelopment of a goal programming model for optimization of truck allocation in open pit mines
Truck and shovel operations comprise approximately 60% of the total operating costs in open pit mines. In order to increase productivity and reduce the cost of mining operations, it is essential to manage the equipment used with high efficiency. In this work, the chance-constrained goal programing (CCGP) model presented by Michalakopoulos and Panagiotou is developed to determine an optimal truc...
متن کاملذخیره در منابع من
با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید
عنوان ژورنال:
- European Journal of Operational Research
دوره 177 شماره
صفحات -
تاریخ انتشار 2007