Bicriteria Resource Allocation Problem in Pert Networks
نویسنده
چکیده
We develop a bicriteria model for the resource allocation problem in PERT networks, in which the total direct costs of the project as the first objective, and the mean of project completion time as the second objective are minimized. The activity durations are assumed to be independent random variables with either exponential or Erlang distributions, in which the mean of each activity duration is a non-increasing function of the amount of resource allocated to it. The direct cost of each activity is assumed to be a non-decreasing function of the amount of resource allocated to it. Finally, we use the goal attainment method to solve the related bicriteria optimal control problem numerically, by converting this problem to a related bicriteria nonlinear programming, and obtain the optimal values of the resources allocated to the activities.
منابع مشابه
Bicriteria Resource Allocation Problem in Pert Networks
We develop a bicriteria model for the resource allocation problem in PERT networks, in which the total direct costs of the project as the first objective, and the mean of project completion time as the second objective are minimized. The activity durations are assumed to be independent random variables with either exponential or Erlang distributions, in which the mean of each activity duration ...
متن کاملA Multi Objective Fibonacci Search Based Algorithm for Resource Allocation in PERT Networks
The problem we investigate deals with the optimal assignment of resources to the activities of a stochastic project network. We seek to minimize the expected cost of the project include sum of resource utilization costs and lateness costs. We assume that the work content required by the activities follows an exponential distribution. The decision variables of the model are the allocated resourc...
متن کاملA heuristic method for consumable resource allocation in multi-class dynamic PERT networks
This investigation presents a heuristic method for consumable resource allocation problem in multi-class dynamic Project Evaluation and Review Technique (PERT) networks, where new projects from different classes (types) arrive to system according to independent Poisson processes with different arrival rates. Each activity of any project is operated at a devoted service station located in a n...
متن کاملResource allocation in multi-server dynamic PERT networks using multi-objective programming and Markov process
In this research, both resource allocation and reactive resource allocation problems in multi-server dynamic PERT networks are analytically modeled, where new projects are expected to arrive according to a Poisson process, and activity durations are also known as independent random variables with exponential distributions. Such system is represented as a queuing network, where multi servers at ...
متن کاملA heuristic method for consumable resource allocation in multi-class dynamic PERT networks
This investigation presents a heuristic method for consumable resource allocation problem in multi-class dynamic Project Evaluation and Review Technique (PERT) networks, where new projects from different classes (types) arrive to system according to independent Poisson processes with different arrival rates. Each activity of any project is operated at a devoted service station located in a node...
متن کاملذخیره در منابع من
با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید
عنوان ژورنال:
دوره شماره
صفحات -
تاریخ انتشار 2004