Exact algorithms for single-machine scheduling with time windows and precedence constraints

نویسندگان

  • Morteza Davari
  • Erik Demeulemeester
  • Roel Leus
  • Fabrice Talla Nobibon
چکیده

We study a single-machine scheduling problem that is a generalization of a number of problems for which computational procedures have already been published. Each job has a processing time, a release date, a due date, a deadline and a weight representing the penalty per unit-time delay beyond the due date. The goal is to schedule all jobs such that the total weighted tardiness penalty is minimized and both the precedence constraints as well as the time windows (implied by the release dates and the deadlines) are respected. We develop a branch-and-bound algorithm that solves the problem to optimality. Computational results show that our approach is effective in solving medium-sized instances, and that it compares favorably with existing methods for special cases of the problem.

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Single Machine Scheduling Problem with Precedence Constraints and Deteriorating Jobs

This paper considers the single machine scheduling problem with precedence constraints and deteriorating jobs. A mathematical model based on binary integer programming (BIP) is developed. By these precedence constraints, jobs can not start before completion of its all predecessors. The represented model is in two steps, in step one the earliest starting time of each job is computed, then the re...

متن کامل

SINGLE MACHINE DUE DATE ASSIGNMENT SCHEDULING PROBLEM WITH PRECEDENCE CONSTRAINTS AND CONTROLLABLE PROCESSING TIMES IN FUZZY ENVIRONMENT

In this paper, a due date assignment scheduling problem with precedence constraints and controllable processing times in uncertain environment is investigated, in which the basic processing time of each job is assumed to be the symmetric trapezoidal fuzzy number, and the linear resource consumption function is used.The objective is to minimize the crisp possibilistic mean (or expected) value of...

متن کامل

Multi-Objective Unrelated Parallel Machines Scheduling with Sequence-Dependent Setup Times and Precedence Constraints

This paper presents a novel, multi-objective model of a parallel machines scheduling problem that minimizes the number of tardy jobs and total completion time of all jobs. In this model, machines are considered as unrelated parallel units with different speeds. In addition, there is some precedence, relating the jobs with non-identical due dates and their ready times. Sequence-dependent setup t...

متن کامل

An exact algorithm for the precedence-constrained single-machine scheduling problem

This study proposes an exact algorithm for the precedence-constrained singlemachine scheduling problem to minimize total job completion cost where machine idle time is forbidden. The proposed algorithm is an extension of the authors’ previous algorithms for the problem without precedence-constraints and is based on the SSDP (Successive Sublimation Dynamic Programming) method. Numerical experime...

متن کامل

Minimizing the Number of Tardy Jobs in the Single Machine Scheduling Problem under Bimodal Flexible and Periodic Availability Constraints

In single machine scheduling problems with availability constraints, machines are not available for one or more periods of time. In this paper, we consider a single machine scheduling problem with flexible and periodic availability constraints. In this problem, the maximum continuous working time for each machine increases in a stepwise manner with two different values allowed. Also, the durati...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:
  • J. Scheduling

دوره 19  شماره 

صفحات  -

تاریخ انتشار 2016