Shahram Shadrokh

Department of Industrial Engineering, Sharif University of Technology, Tehran, Iran,

[ 1 ] - The preemptive resource-constrained project scheduling problem subject to due dates and preemption penalties: An integer programming approach

Extensive research has been devoted to resource constrained project scheduling problem. However, little attention has been paid to problems where a certain time penalty must be incurred if activity preemption is allowed. In this paper, we consider the project scheduling problem of minimizing the total cost subject to resource constraints, earliness-tardiness penalties and preemption penalties, ...