In this chapter, we review the sequence of events that resulted in the negotiated contractor work package and the subsequent string of contract modifications (see also Appendix A). It all began with a budget total established by the Navy in 1992. This was modified over the remainder of the decade in annual Navy budgets. The Navy, meanwhile, planned the work to be undertaken in the RCOH. NNS sub...