A Continuous Multi-resources cumulative Constraint with Positive-Negative Resource Consumption-Production

نویسندگان

  • Nicolas Beldiceanu
  • Emmanuel Poder
چکیده

This article first introduces an extension of the classical cumulative constraint: each task is no more a rectangle but rather a sequence of contiguous trapezoid sub-tasks with variable duration and heights. The resource function is no more constant but is a positive or negative piecewise linear function of time. Finally, a task is no more pre-assigned to one resource, but to a task corresponds a set of possible resource assignments. In this context, this article provides an O(p · (log p+ q)) for computing all the cumulated resource profiles where q is the number of resources and p is the total number of trapezoid sub-tasks of all the tasks.

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

A New Multi-resource cumulatives Constraint with Negative Heights

This paper presents a new s cumulative constraint which generalizes the original cumulative constraint in different ways. The two most important aspects consist in permitting multiple cumulative resources as well as negative heights for the resource consumption of the tasks. This allows modeling in an easy way new scheduling and planning problems. The introduction of negative heights has forced...

متن کامل

Optimization of an energy based bi-objective multi skilled resource investment project scheduling problem

Growing concern in the management of energy due to the increasing energy costs, has forced managers to optimize the amount of energy required to provide products and services. This research integrates an energy-based resource investment project-scheduling problem (RIP) under a multi-skilled structure of the resources. The proposed energy based multi skilled resource investment problem (EB-MSRIP...

متن کامل

Filtering for a Continuous Multi-Resources cumulative Constraint with Resource Consumption and Production

Within the framework of continuous and multiresources cumulative constraints, a task T expresses a piecewise linear resource function and is represented by a sequence of p contiguous trapezoid sub-tasks with variable durations and heights. In this context, this paper provides an algorithm in O(p) for filtering the resource assignment and the temporal attributes of such a task, according to a tr...

متن کامل

Multi-objective scheduling and assembly line balancing with resource constraint and cost uncertainty: A “box” set robust optimization

Assembly lines are flow-oriented production systems that are of great importance in the industrial production of standard, high-volume products and even more recently, they have become commonplace in producing low-volume custom products. The main goal of designers of these lines is to increase the efficiency of the system and therefore, the assembly line balancing to achieve an optimal system i...

متن کامل

The resource-constraint project scheduling problem of the project subcontractors in a cooperative environment: Highway construction case study

Large-scale projects often have several activities which are performed by subcontractors with limited multi-resources. Project scheduling with limited resources is one of the most famous problems in the research operations and optimization cases. The resource-constraint project scheduling problem (RCPSP) is a NP-hard problem in which the activities of a project must be scheduled to reduce the p...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:

دوره   شماره 

صفحات  -

تاریخ انتشار 2007