Solving the flexible job shop problem by hybrid metaheuristics-based multiagent model

نویسندگان

  • Houssem Eddine Nouri SOIE-COSMOS, École Nationale des Sciences de l’Informatique, Université de la Manouba, Tunis, Tunisia
  • Khaled Ghe´dira SOIE-COSMOS, École Nationale des Sciences de l’Informatique, Université de la Manouba, Tunis, Tunisia
  • Olfa Belkahla Driss École Supérieure de Commerce de Tunis, Université de la Manouba, Tunis, Tunisia
چکیده مقاله:

The flexible job shop scheduling problem (FJSP) is a generalization of the classical job shop scheduling problem that allows to process operations on one machine out of a set of alternative machines. The FJSP is an NP-hard problem consisting of two sub-problems, which are the assignment and the scheduling problems. In this paper, we propose how to solve the FJSP by hybrid metaheuristics-based clustered holonic multiagent model. First, a neighborhood-based genetic algorithm (NGA) is applied by a scheduler agent for a global exploration of the search space. Second, a local search technique is used by a set of cluster agents to guide the research in promising regions of the search space and to improve the quality of the NGA final population. The efficiency of our approach is explained by the flexible selection of the promising parts of the search space by the clustering operator after the genetic algorithm process, and by applying the intensification technique of the tabu search allowing to restart the search from a set of elite solutions to attain new dominant scheduling solutions. Computational results are presented using four sets of well-known benchmark literature instances. New upper bounds are found, showing the effectiveness of the presented approach.

برای دانلود باید عضویت طلایی داشته باشید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Parallel hybrid metaheuristics for the flexible job shop problem

A parallel approach to flexible job shop scheduling problem is presented in this paper. We propose two double-level parallel metaheuristic algorithms based on the new method of the neighborhood determination. Algorithms proposed here include two major modules: the machine selection module refer to executed sequentially, and the operation scheduling module executed in parallel. On each level a m...

متن کامل

Solving the Flexible Job Shop Problem on Multi-GPU

We propose the new framework of the distributed tabu search metaheuristic designed to be executed using a multi-GPU cluster, i.e. cluster of nodes equipped with GPU computing units. We propose a hybrid single-walk parallelization of the tabu search, where hybridization consists in examining a number of solutions from a neighborhood concurrently by several GPUs (multi-GPU). The methodology is de...

متن کامل

Solving the continuous flow-shop scheduling problem by metaheuristics

Continuous flow-shop scheduling problems circumscribe an important class of sequencing problems in the field of production planning. The problem considered here is to find a permutation of jobs to be processed sequentially on a number of machines under the restriction that the processing of each job has to be continuous with respect to the objective of minimizing the total processing time (flow...

متن کامل

solving flexible job-shop scheduling problem using hybrid algorithm based on gravitational search algorithm and particle swarm optimization

job shop scheduling problem has significant importance in many researchingfields such as production management and programming and also combinedoptimizing. job shop scheduling problem includes two sub-problems: machineassignment and sequence operation performing. in this paper combination ofparticle swarm optimization algorithm (pso) and gravitational search algorithm(gsa) have been presented f...

متن کامل

A Novel Hybrid Method for Solving Flexible Job-Shop Scheduling Problem

For the purpose of solving the flexible job-shop scheduling problem (FJSP), an improved quantum genetic algorithm based on earliness/tardiness penalty coefficient is proposed in this paper. For minimizing the completion time and the job-shop cost, a simulation model was established firstly. Next, according to the characteristics of the due in production, a double penalty coefficient was designe...

متن کامل

منابع من

با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

ذخیره در منابع من قبلا به منابع من ذحیره شده

{@ msg_add @}


عنوان ژورنال

دوره 14  شماره 1

صفحات  -

تاریخ انتشار 2018-03-01

با دنبال کردن یک ژورنال هنگامی که شماره جدید این ژورنال منتشر می شود به شما از طریق ایمیل اطلاع داده می شود.

میزبانی شده توسط پلتفرم ابری doprax.com

copyright © 2015-2023