Journal: :Computers & Industrial Engineering 2014
Richard Quibell Vitaly A. Strusevich

The paper considers a three-machine shop scheduling problem to minimize the makespan, in which the route of a job should be feasible with respect to a machine precedence digraph with three nodes and one arc. For this NP-hard problem that is related to the classical flow shop and open shop models, we present a simple 1.5approximation algorithm and an improved 1.4-approximation algorithm.

Journal: :European Journal of Operational Research 2010

Journal: :Kybernetika 2011
Jan Pelikán

The subject of this paper is a flow-shop based on a case study aimed at the optimisation of ordering production jobs in mechanical engineering, in order to minimize the overall processing time, the makespan. The production jobs are processed by machines, and each job is assigned to a certain machine for technological reasons. Before processing a job, the machine has to be adjusted; there is onl...

Journal: :Sustainability 2021

The flexible job shop problem (FJSP) has been studied in recent decades due to its dynamic and uncertain nature. Responding a system’s perturbation an intelligent way with minimum energy consumption variation is important matter. Fortunately, thanks the development of artificial intelligence machine learning, lot researchers are using these new techniques solve rescheduling shop. Reinforcement ...

  In this paper, we consider a flow shop scheduling problem with bypass consideration for minimizing the sum of earliness and tardiness costs. We propose a new mathematical modeling to formulate this problem. There are several constraints which are involved in our modeling such as the due date of jobs, the job ready times, the earliness and the tardiness cost of jobs, and so on. We apply adapte...

Journal: :IEICE Transactions 2008
Ruey-Shun Chen Yung-Shun Tsai Arthur Tu

In this study we propose a manufacturing control framework based on radio-frequency identification (RFID) technology and a distributed information system to construct a mass-customization production process in a loosely coupled shop-floor control environment. On the basis of this framework, we developed RFID middleware and an integrated information system for tracking and controlling the manufa...

2013
Jaroslaw Pempera Czeslaw Smutnicki Dominik Zelazny

We consider the flow shop scheduling problem with minimizing two criteria simultaneously: the total completion time (makespan) and the sum of tardiness of jobs. The problem is strongly NP-hard, since for each separate criteria the problem is strongly NP-hard. There is a number of heuristic algorithms to solve the flow shop problem with various single objectives, but usage of those heuristics to...

2013
Mohammad Mirabi

Flow-shop scheduling problem (FSP) deals with the scheduling of a set of jobs that visit a set of machines in the same order. The FSP is NP-hard, which means that an efficient algorithm for solving the problem to optimality is unavailable. To meet the requirements on time and to minimize the make-span performance of large permutation flow-shop scheduling problems in which there are sequence dep...

Journal: :J. Scheduling 2011
Peter Brucker Natalia V. Shakhlevich

We study an inverse counterpart of the two machine flow-shop scheduling problem that arises in the context of inverse optimization. While in the forward scheduling problem all parameters are given and the objective is to find job sequence(s) for which the value of the makespan is minimum, in the inverse scheduling the exact values of processing times are unknown and they should be selected with...

2006
Tzung-Pei Hong Pei-Ying Huang Gwoboa Horng

In simple flow shop problems, each machine operation center includes just one machine. If at least one machine center includes more than one machine, the scheduling problem becomes a flexible flow-shop problem. Recently, group scheduling has also been proposed and discussed. In the group scheduling, each job belongs to a specific group and all the jobs are processed group by group. In this pape...